Guides for installation and assembly of the LulzBot line of products made by FAME 3D LLC.
Parts:
2x- 24AWG stranded Red wire, 1300mm in length [EL-WR0103]
2x- 24AWG stranded Orange wire, 1300mm in length [EL-WR0104]
6x- 22-24AWG female terminals for red an orange [EL-MS0059]
1x- 4 position female connector [EL-MS0062]
1x- 2 position female connector [PC-CN0001]
1x- poly bags [SH-PG0003]
Tools: - Wire cutter
Wire stripper
Wire crimper
Measuring device
Cut 1300mm lengths of 24AWG stranded Red (2 ea) and 24AWG stranded Orange (2 ea)
Orange wire, Strip 4mm of insulation on each side of cut
Red wire, one end of each wire only, strip 4mm of insulation
Red wire, other end of each wire only, Plan for 2mm of insulation strip at 6mm
Apply 22-24AWG female terminals [EL-MS0059] to each stripped wire ends, ensure each terminal is crimped onto both the wire and insulation of each cut end
Plug Red wire into positions 3 & 4 of 4 position female connector [EL-MS0062]
Plug Orange wire into position 1 of the 4 position female connector [EL-MS0062]; Plug opposite end to position 2 of the 2 position connector [PC-CN0001]
Plug Orange wire into position 2 of the 4 position female connector [EL-MS0062]; Plug opposite end to position 1 of the2 position connector [PC-CN0001]
Verify wires are plugged in to their proper positions